Project

General

Profile

Actions

Task #17

closed
FT FT

Transfer GUI files from old kca 0.1 to new MVC system

Task #17: Transfer GUI files from old kca 0.1 to new MVC system

Added by Felix Tiede over 14 years ago. Updated over 14 years ago.

Status:
Completed
Priority:
Normal
Assignee:
Target version:
Start date:
01/01/2012
Due date:
02/10/2012
% Done:

70%

Estimated time:
20:00 h
Spent time:

Description

The current GUI is very basic, mainly consisting of authority and certificate selection widgets. Dialogs should be easy to transfer.

FT Updated by Felix Tiede over 14 years ago Actions #1

  • % Done changed from 0 to 30

FT Updated by Felix Tiede over 14 years ago Actions #2

  • % Done changed from 30 to 40

Fixed some bugs in main display - connected authority selection with certificate display.

FT Updated by Felix Tiede over 14 years ago Actions #3

  • % Done changed from 40 to 50

FT Updated by Felix Tiede over 14 years ago Actions #4

  • % Done changed from 50 to 60

FT Updated by Felix Tiede over 14 years ago Actions #5

  • Due date changed from 01/29/2012 to 02/03/2012

FT Updated by Felix Tiede over 14 years ago Actions #6

  • Due date changed from 02/03/2012 to 02/10/2012

Due date moved as transitioning the GUI to MVC is not as simple as assumed.

FT Updated by Felix Tiede over 14 years ago Actions #7

  • % Done changed from 60 to 70

Request signing dialog now operational. Though not thoroughly tested.

FT Updated by Felix Tiede over 14 years ago Actions #8

  • Status changed from New to In Progress

FT Updated by Felix Tiede over 14 years ago Actions #9

  • Status changed from In Progress to Completed

All GUI parts have been transferred, though neither authority importing nor request signing is as yet functional.

Actions

Also available in: PDF Atom